We have received our first shipment of metal and should receive the remainder this week. Whether we receive the remainder or not we will start cutting metal this week! We also have leveled all of our work tables in preparation for the fuselage build. Our wing wood is still on back order and hopefully we should have it in about three weeks. Things look like they will all come together this week and we should be rolling on.